Pima Elementary School

3/23/18 – Framing is underway for the new classroom building, and the center slab has been poured. The school’s new circular drive is also starting to take shape.

Construction Timeline:

  • December 2017 – Shovels in, fences up! Ground work
  • January 2018 – Vertical construction begins
  • Summer 2018 – New buildings open to students and staff
Timelapse Video

Please note, this camera is faced away from the current school buildings and will not show any children - only construction crews.
Watch a timelapse of the Pima Traditional construction.

Pima Documents & Links

Floorplans for the Admin and Multipurpose buildings are currently under review.

Rebuild Committee Members

Thank you very much to the parents and staff members who signed up to be part of this exciting process. The committee will represent the community in providing input on the design of the new campus.

Lead:
Alexis Cruz-Freeman - Principal

Committee Members:
Damien Mendoza - Parent
Josh Friedman - Parent & PTO President
John Selkirk - Teacher
Colleen Felix - Teacher
Janet Navarro - Teacher
Kimberly Mills - Assistant Principal
Paul Thomas - Facilities Coordinator
Dan Bentel - Parent
Melissa Willis - Parent

 

Pima Elementary School Gallery

construction-cam-pima
Pima_1
Pima_10
Pima_11
Pima_12
Pima_13
Pima_14
Pima_15
Pima_16
Pima_18
Pima_19
Pima_2
Pima_20
Pima_21
Pima_22
Pima_23
Pima_24
Pima_25
Pima_26
Pima_27
Pima_28
Pima_29
Pima_3
Pima_30
Pima_31
Pima_32
Pima_33
Pima_4
Pima_5
Pima_6
Pima_7
Pima_8
Pima_9