Community Meeting Alert: Hopi Elementary School is excited to share final designs for its new school buildings at a community meeting on September 27 at 6:00 pm in the Hopi cafeteria. Thank you to everyone who came to the last community meeting to ask questions and give feedback. The Hopi Rebuild Committee, made up of parents, teachers and neighbors, has spent the last five months working with architects and district leadership on both interior and exterior designs. Come see the results of that collaboration and learn about the next phase of construction. 

Bond & Capital Override Information

Your Tax Dollars at Work - Bond & Override Updates

Cheyenne Updates

9/6/2017 - Cheyenne students, SUSD Governing Board, Superintendent Birdwell, Cheyenne Admin and Cheyenne PTO broke ground on the new Cheyenne Gymnasium and Science Labs. Construction is on track for 8th graders to graduate in their new gym next spring.

  • slide
  • slide
  • slide
  • slide
  • slide
  • slide

Cheyenne Construction

Click here to Expand - Cheyenne Documents & Links

Existing Site
    • PNG Download (Updated 4/27/17)
Site Plan
    • PDF Download (Updated 5/27/17)
Updated Site Map
    • JPG Download (Updated 8/8/17)
Proposed Traffic Plan
    • PNG Download (Updated 4/27/17)
Proposed Gym Floor Plan
     • PNG Download (Updated 6/20/17)
Proposed Lab Locations
    • PNG Download (Updated 5/1/17)
Science Labs
    • PDF Download (Updated 5/23/17)
Proposed Gym Exteriors
    • PNG Download (Updated 5/23/17)
Existing Administration Area
    • PNG Download (Updated 4/27/17)
Proposed Administration Area
    • PNG Download (Updated 4/27/17)
Site Logistics
    • PDF Download (Updated 5/11/17)


 


 

Hohokam Updates

8/9/2017 – A tentative construction timeline is now in place for Hohokam (see below). The new school is set to open in summer of 2019. Architects and SUSD leaders are looking forward to working with Hohokam’s new rebuild committee as plans take shape over the next year.

Construction Timeline:

May, 2018 – Shovels in, fences up! Ground level work
Summer, 2018 – Vertical construction begins
Summer, 2019 – New buildings open to students and staff

Hohokam Construction

Click here to Expand - Hohokam Documents & Links

Existing Site
     • JPG Download (Updated 4/27/17)
Site Plan
     • JPG Download (Updated 5/23/17)
Site Plan v2
    • PDF Download (Updated 5/23/17)
Phase 1, Phase 2, Phase 3 - Coming Soon

Click to Expand - Hohokam Rebuild Committee

The Hohokam Rebuild Committee has been selected! Thank you very much to the parents and staff members who signed up to be part of this exciting process. The committee will represent the community in providing input on the design of the new campus.

Lead:
Principal Chuck Rantala-Principal

Committee Members:
Aimee Yates-Principal Intern
Linda Tardie-Staff
Jessica Valencia-Staff
Judy Edmondson-Staff
Mike Peabody-Parent
Andrew Jazwa-Parent
Susie Clouse-Parent
Terri Mann-Facility Coordinator


 


 

Hopi Updates

9/15/2017 – New color-coded floorplans of Hopi’s planned classroom, multi-purpose and administrative buildings show what purpose each area will serve. You can find those new floorplans in this section under “Hopi Documents and Links” 

Updated Construction Timeline
October, 2017 – Shovels in, fences up! Ground level work
November, 2017 – Vertical construction begins
Summer, 2018 – New buildings open to students and staff

Hopi Construction

Click here to Expand - Hopi Documents & Links

Existing Site
     • PNG Download (Updated 4/27/17)
Construction Plan
     • PDF Download (Updated 7/26/17)
Phase 1
     • JPG Download (Updated 9/18/17)
Phase 2
     • JPG Download (Updated 9/18/17)
Phase 3
     • JPG Download (Updated 9/18/17)
Classroom Pod
     • Classroom Pod Render (Updated 6/20/2017)
Multi-Purpose Building Floorplan
     • Multi-Purpose Building Floorplan (Updated 9/15/17)
Admin Building Floorplan
     • Admin Building Floorplan (Updated 9/15/17)
Classroom Building Floorplan
     • Classroom Building Floorplan (Updated 9/15/17)
Exterior Design
     • Exterior Design 1 (Updated 9/5/17)
     • Exterior Design 2 (Updated 9/5/17)
     • Exterior Design 3 (Updated 9/5/17)
     • Exterior Design 4 (Updated 9/5/17)
     • Exterior Design 5 (Updated 9/5/17)

Click here to Expand - Hopi Rebuild Committee

The Hopi Rebuild Committee (representing parents, teachers, and community members) is meeting weekly to give input on the design of the new school.

Lead:
Principal Tamara Jagodzinski

Committee Members:
Patti Dietz – parent/neighbor 
Chris Janson – parent/neighbor
Andrew Seidenberg - parent
Craig Demarco – parent
Casey Christensen - parent/neighbor/alternative committee member
Tim Marriott – teacher/Site Council
Debbie Voris - teacher
Dave Hanlon - teacher
Jacqueline Comerford - teacher
John Strippelman – facilities coordinator


 


 

Pima Updates

9/3/2017 – Exterior designs and a floorplan for the new Pima classroom building are now complete! You can view the designs in the Pima Documents and Links section of this page

Construction Timeline:
November, 2017 – Shovels in, fences up! Ground work
December, 2017 – Vertical construction begins
Summer, 2018 – New buildings open to students and staff

Pima Construction

Click Here to Expand - Pima Documents & Links

Floorplans for the Admin and Multipurpose buildings are currently under review.
Existing Site
     • JPG Download (Updated 4/27/17)
Site Plan
     • JPG Download (Updated 6/23/17)
Classroom Building Floorplan
    • PNG Download (Updated 9/2/2017)
Exterior Design
    • Exterior Design 1 (Updated 9/5/2017)
    • Exterior Design 2 (Updated 9/5/2017)
    • Exterior Design 3 (Updated 9/5/2017)
    • Exterior Design 4 (Updated 9/5/2017)
Construction Phases
    • PDF Download (Updated 9/7/2017)
Interior Classroom Windows
    • PDF Download (Updated 9/18/2017)

Click here to Expand - Pima Rebuild Committee Members

The Pima Rebuild Committee has been selected! Thank you very much to the parents and staff members who signed up to be part of this exciting process. The committee will represent the community in providing input on the design of the new campus.

Lead:
Alexis Cruz-Freeman - Principal

Committee Members:
Damien Mendoza - Parent
Josh Friedman - Parent & PTO President
John Selkirk - Teacher
Colleen Felix - Teacher
Janet Navarro - Teacher
Kimberly Mills - Assistant Principal
Paul Thomas - Facilities Coordinator
Dan Bentel - Parent
Melissa Willis - Parent

 


 


 

Coronado High School Track & Field
Construction

Coronado High School Track & Field Coronado High School Track & Field
Coronado Track & Field Construction Video

Coronado Track & Field Construction Video

Chaparral High School Track & Field
Construction

Chaparral Track & Field Chaparral Track & Field
Chaparral Track & Field Construction Video

Chaparral Track & Field Construction Video

Saguaro High School Track & Field
Construction

Saguaro High School Track & Field Saguaro High School Track & Field
Saguaro Track & Field Construction Video

Saguaro Track & Field Construction Video

Links & Documents

ATTENTION: Regular Board Meeting Documents are currently being migrated to the new website
     
    September 12, 2017
    
Spotlights - Bond / Capital Override Financial Update
     • Video - Bond / Capital Override Financial Update

     June 20, 2017
     
Minutes - Hopi pre-construction approval, Cheyenne full construction approval, Pima contractor approval
     • Spotlights - Hopi pre-construction approval, Cheyenne full construction approval, Pima contractor approval
     • Video - Hopi pre-construction approval, Cheyenne full construction approval, Pima contractor approval

     June 6, 2017
     • 
Minutes - Cheyenne pre-construction approval
     • Spotlights - Cheyenne pre-construction approval
     • Video - Cheyenne pre-construction approval

     May 4, 2017
     • 
Audio - Contractor approved for Hohokam & Cheyenne

     April 25, 2017
     • Minutes -  
     • Spotlights - RFQ Hopi Rebuild & Chaparral, Coronado, Saguaro Track Improvements
     • Video -  RFQ Hopi Rebuild & Chaparral, Coronado, Saguaro Track Improvements

     March 21, 2017
     • Minutes - Pima Rebuild Approval
     • Spotlights - Pima Rebuild Approval
     • Video - Pima Rebuild Approval

     December 13, 2016
     • Minutes - Hopi & Hohokam Rebuild Approval
     • Spotlights - Hopi & Hohokam Rebuild Approval
     • Video - Hopi & Hohokam Rebuild Approval
     

Regular Board Meeting Presentations

     • Bond Presentation (PDF) - 04/25/16 - Procurement Engagement Timeline
     • Bond Presentation (PDF) - 12/13/16 - Hopi/ Hohokam Elementary

Bond Infographic
     • PDF Download (updated 4/20/17)

Bond Project Input Form

Your input is important to this process. Please use this form to share your comments, questions and concerns. While we are not able to respond to every submission individually, we will read all of them to identify the most common or pressing themes, which may be addressed in a public forum or in our FAQ sections. Thank you.

Required
Required
Required
Required

Jump To...

Weekly Updates Archive:

Sign Up for Weekly Bond & Override Information Newsletter

Click on your Learning Community to see the Bond & Override Improvement Projects underway at your school.


In addition to those improvements, override dollars will also help pay for new furniture, playground improvements, instructional materials and more. School needs are currently being assessed to determine when and where those additional dollars will be spent.

Financial Summaries

Building Construction Budget (9/12/17)
Bond Expenditures (9/12/17)
School Improvements (9/12/17)

Bond & Override Committee Link