FACILITIES
SERVICES PROJECT STATUS REPORT
Presented to the Governing Board Sept. 3, 2002
By Bill Johnson, Ed.D., Chief of Facilities and Operations
BOND FUND PROJECTS
- Copper Ridge
Construction of new elementary school-completion by mid-September
- Chaparral
Construction of replacement music building-complete
Fire Access Lane-substantially complete by start of school
- Cheyenne
Construction of seventh grade pod-complete
- Cocopah
Construction of new cafeteria/classroom building-completion by start of school
Remodel existing cafeteria into science classrooms-completion by mid-September
- Mohave
Construction of new cafeteria building-completion by start of school
Remodel existing cafeteria into science classrooms-completion by late-August
- Supai
Construction of replacement school-completion by start of school
Demo existing school-complete
Develop new fields-substantially complete by start of school
- Tavan
Construction of Phase 3 classrooms and media center-complete
- High School Projects
Arcadia South Locker Rooms-completion by start of school
Arcadia Bldg 400-completion by late September
Arcadia-Misc. punch-list items-completion by late September
Chaparral-Misc. punch-list items-completion by late September
Coronado-Theater Renovations-substantially complete by start of school
SCHOOL FACILITIES BOARD
PROJECTS (Students First)
- ANLC
New Roof-Bldg F-in progress, coordinating construction schedule with school
New Classroom Lighting-Building H-completion by start of school
Site Drainage-in progress, coordinating construction schedule with school
- Chaparral
Grease Interceptor-out to bid
Roof Replacement-Multiple Buildings-out to bid
A/C Replacement-Bldg E-out to bid
HVAC Controls-Bldgs B, C and L-out to bid
- Cherokee
Grease Interceptor-in progress, coordinating construction schedule with school
Roof Replacement-Multiple Buildings-in progress, coordinating construction
schedule with school
A/C Replacement-Kitchen-in progress, coordinating construction schedule with
school
- Cocopah
Lighting Improvements-Bldg K-completion by start of school
Roof Replacement - Multiple Buildings - start construction mid-September
Galvanized Pipe Replacement-Multiple Buildings-completion by start of school
A/C Replacement-Bldg I-completion by start of school
Sewer System Upgrade - start construction mid-September
- Coronado
Store Front Door Replacement-out to bid
Roof Replacement-Gym-out to bid
500 T Chiller Replacement-completion by start of school
- Hohokam
Drainage Correction-Asphalt Play Area-out to bid
A/C Replacement-Bldg L-out to bid
- Hopi
New Roof-All buildings-in progress, coordinating construction schedule with
school
New Doors and Windows-Multiple Buildings-in progress, coordinating construction
schedule with school
Heat Pump Safety Grilles-in progress, coordinating construction schedule with
school
Cafeteria Boiler Replacement-in progress, coordinating construction schedule
with school
Cafeteria A/C Replacement-in progress, coordinating construction schedule
with school
A/C Sound Solution-Multiple Buildings-in progress, coordinating construction
schedule with school
Site Fencing-in progress, coordinating construction schedule with school
- Ingleside
New Roofs-Multiple Buildings-in progress, coordinating construction schedule
with school
Window Replacement-Multiple Buildings-in progress, coordinating construction
schedule with school
Boiler Replacement-in progress, coordinating construction schedule with school
Heat Pump Safety Grilles-in progress, coordinating construction schedule with
school
- Kiva
ADA Restroom modifications-Kindergarten-out to bid
Window Replacement-Multiple Buildings-out to bid
A/C Sound Solution-Multiple Buildings-out to bid
- Mohave
A/C Replacement-Bldg A and E-in progress, coordinating construction schedule
with school
Roof Replacement-Bldg C and E3-in progress, coordinating construction schedule
with school
Window/Door Replacement-Multiple Buildings-in progress, coordinating construction
schedule with school
Energy Management Controls-Multiple Buildings-completion by start of school
- Navajo
Site Fencing-in progress, coordinating construction schedule with school
A/C Replacement-Bldgs G and F-in progress, coordinating construction schedule
with school
- Pima
Site Fencing-out to bid
A/C Replacement-Building M-out to bid
- Tavan Annex
A/C Replacement-completion by start of school
- Tonalea
Bus Drop-off-out to bid
Site Drainage-out to bid
- Yavapai
Site Fencing-out to bid
Roof Replacement-Multiple Buildings-completion by start of school
A/C Replacement-Bldg D-out to bid
BUILDING SERVICES PROJECTS
- Tavan Annex
Renovation-completion by start of school
- Multiple Sites
Carpet Replacement-completion by start of school
- Cochise-Modular Buildings
Removal of existing campus-completion by start of school
- Saguaro
Rebuild Chiller-completion by start of school