Timeline: As of August, 1999,
all of the bonds have been sold. The total amount of money in the bond
budget is $106,670,000.00. The current plans anticipate that all of these
funds will be spent by the summer of 2002.
Questions: Anyone with questions
about the bond program should be able to contact their school principal
for information. Additional information can be obtained from Bill Johnson,
Assistant Superintendent for Facilities & Operations (480-484-6143).
Budget: Below is a brief summary
of the bond budget. Additional detailed information with regard to individual
school projects is being provided on 3D-International's
Web site. 3D-International (3D-I) is a construction management firm
that the district has hired to manage all of the construction projects
being funded by the bond.
New School Construction: Copper
Ridge (DC Ranch area) $23,000,000
(Phase I - $19,000,000 Phase II - $4,000,000)
Remodeling of Existing Schools:
$63,190,000
A brief sampling of the kinds of projects being
completed is listed below. A more complete update of school projects will
be contained on the Web site (http://www.3di.com/pws)
coordinated by 3D-International. Their Web site will continually be updated
as new information is obtained.
a. A new school is being constructed in North
Scottsdale in the DC Ranch neighborhood. The school has officially been
named Copper Ridge School. It is being built in two phases. When both
phases are completed, the school will house students in kindergarten
through eighth grade. The middle school portion is being built first.
This first phase will include the administration, cafeteria, gymnasium
and play fields. Once the first phase is completed, we hope to add the
elementary classrooms (Phase II) immediately. Phase I is scheduled to
be completed in December 2000. We hope to have Phase II finished by
August 2001.
b. All-weather tracks: All weather tracks
are currently being installed at each of our five high schools. Arcadia
H.S., who already has an all-weather track, is having its track resurfaced.
Each of the other four high schools should have its new track ready
for spring track competition.
c. Replacement of Cochise School: When Cochise
School was originally built, all of its buildings were modular structures.
They are currently in poor condition. As a part of the bond program,
a new facility adjacent to the existing school will be built. This new
school is scheduled to open in August 2001.
d. Replacement of portable classrooms: Many
of our schools have some outdated portable classrooms. As a part of
this bond program, all portable classrooms are scheduled to be replaced
with permanent structures. Once the new classrooms are built, the portables
will be removed.
e. Upgrading of mechanical systems: Many of
the older schools have heating and cooling systems that are completely
outdated. As a part of this bond program, we will undertake the replacement
of most of the old mechanical systems. This will include new units at
campuses like Ingleside, Kiva, Cherokee and Tavan, just to name a few.
f. Renovation of Tavan School: The Board approved
a major renovation at Tavan Elementary School. Tavan is the oldest school
in the district. Currently, students attend classes on both the north
and south side of Osborn Road. After the major renovation, all student
classrooms should be on the north side of Osborn and all mechanical
systems will be updated.
g. Every campus: Nearly every campus will
receive some amount of remodeling. The older schools will receive substantial
budgets for remodeling. Newer schools will receive funds for things
like increased security. For additional detail regarding the budget
and projects for each school site, please refer to the Web site (http://www.3di.com/pws)
maintained by 3D-I, the construction management firm coordinating the
remodeling work.
Bond Oversight Committee: As part of the commitment
to Scottsdale voters that the funds would be spent in a manner consistent
with promises made to the community, a Bond Oversight Committee was
established. The committee is comprised of individuals who have demonstrated
a history of civic involvement. In addition, none of the members have
children in any Scottsdale school. That was to ensure that they would
be impartial with regard to individual school needs. As a result, they
have maintained a districtwide perspective in their efforts to monitor
how bond funds are spent.
The members of the Bond Oversight Committee
are as follows:
Gary Moriarty, Architect (Chairperson)
Ted Beam, Rural/Metro Corporation
George Bosworth, Equity Residential
Tim Bray, Southwest Community Resources
Bonnie Halley, Scottsdale Chamber of Commerce
Pam Krewson, Arts in Education Council
Wendy Lyons, Scottsdale Health Systems
Robert Peirce, Jr., Scottsdale Association
of Realtors
Don Ruff, Bank One Arizona
Diana Smith
Murray Smith, McCormick Homeowners Association
Bill Johnson, Assistant Superintendent
Now that the plan for spending bond funds has
been developed and remodeling projects are underway at all of our schools,
the Bond Oversight Committee meets on a quarterly basis. Meetings are
open to the public. They are held at the Education Center at 3811 North
44th Street in the Board Room. Meetings run from 4:30 P.M. - 6:00 P.M.
For those who cannot attend the meetings, the District will post the minutes
from the meetings on its Web site (www.susd.org)
 |
Many people have asked about the process that
was used in deciding which projects would be addressed with bond funds.
That process began before the ballot was even presented to the public
to vote on. Numerous meetings were held at schools and among community
groups to prioritize the needs of the district. Well before any preliminary
budget was prepared, it was clear that this bond issue would not be adequate
to address all the needs of our aging schools. A commitment was made early
on that the primary focus of this bond sale should be to focus on the
needs of our older schools. Therefore, when anybody looks at the breakdown
on how funds were allocated to each school for remodeling, they can easily
see that the older schools are receiving considerably more money than
the newer schools.
One of the first steps was the development
of facility standards. That process began with an initial inventory of
existing sites. That study was conducted by The Cunningham Group, an architectural
firm specializing in educational settings. With the direction provided
by the Cunningham Group, a series of meetings were held to solicit input
from staff, students, parents and community members on what standards
should guide construction activities in the schools. Approximately a year
was spent on the development of the facility standards. These standards
now provide guidance on various aspects of the school building, and include
recommendations for such things as the size of regular classrooms, art
rooms, cafeterias, etc. In addition, they provide guidance on functions
such as the desired operational effectiveness of heating and cooling equipment,
number of parking places needed, and athletic equity issues for each campus.
Once the standards had been developed, a determination
had to made as to how each of our existing schools matched up to the standards.
Almost another year was spent evaluating each school campus. A team of
architectural firms was hired to visit each school and determine where
the school differed from the building standards. Using the services of
Pinnacle One, a construction management company, each of the variances
from standards was assigned a cost. Using the data received from Pinnacle
One, it would take approximately $300 million to correct all of the deficiencies
and bring every facility up to the standards that were developed.
Since the bond budget only allowed for approximately
$63 million for renovating our schools, a great deal of prioritizing had
to be done. Several concepts guided that prioritization process. The original
promises made to voters prior the bond election were a major factor. Safety
issues at each campus were also given a high priority. It was clearly
a consensus that all mechanical systems (heating, cooling, plumbing, etc.)
at the schools had to be in proper operating condition. A balance was
sought among the different program areas that needed to be upgraded (i.e.
fine arts, athletics, etc.).
During the prioritization process, meetings
were held with school leadership teams to review the projects that had
been identified. Meetings among principals and other staff provided individuals
with opportunities to express concerns with the existing facilities. All
through the development of the plan, the Bond Oversight Committee actively
participated. The Scottsdale School Board met in collaboration with the
Bond Oversight Committee to share ideas and to allow public participation
on how funds should be spent. The resulting plan was approved by the School
Board on Sept. 7, 1999. That plan is now the guiding force for all of
the remodeling work to be completed at each site during the next three
years.
In subsequent meetings, five architectural firms
were approved by the School Board. The five firms are:
| Durrant Architects |
The Stichler Group |
| Orcutt/Winslow |
Gould Evans |
| Saemisch DiBella Murphy |
The School Board also hired the firm of 3D-International
(3D-I) to manage all of the construction projects over the next three
years. They have staff assigned to each of the schools and they will maintain
the bond budget. On a quarterly basis, they will present updates to the
Bond Oversight Committee. In addition, 3D-I is maintaining a Web site
(http://www.3di.com/pws). This Web site will provide updated information
to the entire public on the status projects and budget information.
Each school has been assigned one of the architectural
firms to work with the principal and site leadership team to finalize
each of the projects to be completed. They will work closely with that
firm until the completion of the remodeling program. Additional information
related to specific schools can be found on the
Web site created by 3D-I.
Who made the determination on which projects
were to be funded?
All of us. Principals and other administrators,
teachers, staff, students, the Bond Oversight Committee, parent groups,
and the Board. This is in addition to the community groups who were involved
prior to the promotion and vote on the Bond who made promises to the community
on what would happen if they voted for the bond. The plan approved by
the Board in September allocated $63,190,000 dollars to remodel our schools.
By going to the principal groups with those numbers and plans, the administration
tried to involve them as vehicles for sharing with the general public
at each school.
If your school had some priorities that
were deemed important, why are they not being funded?
This bond was never promoted as a means to solve
or address wish-list items at schools. We never said that schools would
choose their projects. This bond, from the very moment the District went
out to the public, was designed to raise all schools to a common level
of standards. A great deal of time was spent establishing the standards,
comparing schools to the standards and deciding which standards could
be maintained at all sites. Major categories of expenditures and standards
were shared with the voters prior to the measure being approved. It included
such matters as mechanical deficiencies (HVAC, plumbing, electrical),
security, the replacement of portable buildings with permanent structures,
kitchen upgrades, etc. All standards could not be funded, let alone items
that were not standards. Many school priorities did not address districtwide
standards. In addition, compared to more critical items, many school priorities
simply could not be funded with our limited budget.
Why is there such a wide disparity in
the amount of money allocated to the individual schools?
Once again, the funds were promised for bringing
all schools up to district standards. The schools vary greatly in how
they vary from the standards. There was never any inference that the money
would be spent equally among schools. In fact, just the opposite has been
the goal. That is, more money needs to be spent on those schools who need
the greatest amount of work. By and large, that is the older schools.
On the breakdown of expenditures by school and by complex, the plan does
a great job of addressing the needs in the older schools over those requests
from newer schools.
Why isn't there more funding to repair
more roofs?
Monies from the State through the Students First
Capital funding program will be used to augment expenditures from the
bond. A major portion of the Students First (Building Renewal) budget
will be applied to repair roofs. With these additional monies, all roofs,
over the next few years, should be upgraded to meet our standards.
When we looked at what it would take to bring
all schools up to the standards, the cost was well over $300 million.
We have approximately $60 million to address the most severe issues. We
simply have had to prioritize. Hopefully, by focusing our monies on the
oldest and most deserving sites and buildings, we can win the support
from our community for future bond votes. By understanding this whole
picture, we should be able to help all parents and staff realize that
we have numerous challenges to address with a rather restricted budget
(even though $60 million is a lot.)
|